Acts
| Department | Act / GO / Rules | Purpose |
| Industries & Commerce | TG-iPASS Act, 2014 (Act No. 3 of 2014) | Single-window industrial approvals |
| G.O.Ms.No.35 of I&C Dept., Dt.17.06.2015 | TG-iPASS Rules, 2015 | |
| G.O.Ms.No.36 of I&C Dept., Dt.17.06.2015 | Constitution of State & District TG-iPASS Committees | |
| G.O.Ms.No.06 of I&C Dept., Dt.23.03.2026 | Industrial incentives (MSME Policy, 2024) for all categories | |
Time Limits – Establishment
| Time Limits – Establishment | ||||
| S.No | Approval | Department | Time Limits | |
| 1 | 1a | CFE (under water act 1974 & Air act 1981) – Green Category | TSPCB (Consent for Establishment) | 7 days |
| 1b | CFE (under water act 1974 & Air act 1981) – Orange Category | TSPCB | 14 days | |
| 1c | CFE (under water act 1974 & Air act 1981) – Red Category | TSPCB | 21 days (not requiring clearance from Central Government) | |
| 2 | 2a | Power Feasibility & Estimate – Up to 33 KVA connection | DISCOMs (TSSPDCL/TSNPDCL) & TSTRANSCO | 2 days for feasibility, 10 days for estimate |
| 2b | Above 33 KVA connection | DISCOMs & TSTRANSCO | 25 days | |
| 3 | 3 | Factory Plans Approval | Factories Department | 7 days |
| 4 | 4 | Plot Allotment | TSIIC | 14 days |
| 5 | 5 | Land Alienation | CCLA | 30 days |
| 6 | 6 | Change of Land Use | CCLA – under NALA Act | 14 days |
| 7 | 7 | Change of Land Use | HMDA and KUDA | 30 days |
| 8 | 8 | Industrial Building Plan Approval through DPMS software | DT&CP / IALA / HMDA / KUDA | 7 Days for DTCP 14 Days for HMDA/KUDA & IALA *Pre-Scrutiny – 7 Days (for issuing DC Letter) |
| 9 | 9 | Provisional FIRE NOC | Fire Services Department | 7 days (<15 m buildings), 14 days (>15 m buildings) |
| 10 | 10 | Permission to Draw Water (Bore Well Permission) | Ground Water Department | 14 days |
| 11 | 11 | Feasibility of Water Supply | HMWW&SB, Irrigation & CAD dept.,PR&RD, I&C, RWS,GHMC | 14 days |
| 12 | 12 | VAT Registration | Commercial Taxes Department | 1 day (Hyderabad), 3 days (Districts) |
| 13 | 13 | Approval of the Layout and Building Plans | HMDA / TSIIC / MA&UD / PR&RD | 14 days |
| 14 | 14 | License to Store RS, DS | Excise Department | 14 days |
| 15 | 15 | Firm Registration | Registration and Stamps Department | 7 days |
| 16 | 16 | Authorisation under hazardous waste | Telangana State Pollution Control Board (TSPCB) | 21 Days |
| 17 | 17 | NOC for Change of Land use | Irrigation Department | 7 Days |
| 18 | 18 | Permission for felling Non-exempted trees under AP WALTA Act. | Forest Department | 15 Days |
| 19 | 19 | Registration of principal employer’s establishment under provision of The Contracts Labour (Regulation and Abolition) Act, 1970 | LET&F | 30 Days |
| 20 | 20 | License for contractors under provision of The Contracts Labour (Regulation and Abolition) Act, 1970 | LET&F | 30 Days |
| 21 | 21 | Registration under The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 | LET&F | 15 Days |
| 22 | 22 | Registration of Establishment under Inter State Migrants Workmen (RE&CS) Act, 1979 | LET&F | 30 Days |
| 23 | 23 | Electrical Design Approval | CEIG | 14 days |
| 24 | 24 | Registration under Profession Tax | Commercial Tax Department | (1) day |
Time Limits for Operation
| Time Limits for Operation | ||||
| S.No | Clearance | Department | Time Limits | |
| 1 | 1a | CFO (under water act 1974 & Air act 1981) – Green Category | TSPCB | 7 days |
| 1b | CFO (under water act 1974 & Air act 1981)– Orange Category | TSPCB | 14 days | |
| 1c | CFO (under water act 1974 & Air act 1981) – Red Category | TSPCB | 21 days (not requiring Central Government clearances) | |
| 2 | 2 | Factory Licence | Factories Department | 7 days |
| 3 | 3 | Fire Occupancy Certificate | Fire Services Department | 7 days (<15 m buildings), 14 days (>15 m buildings) |
| 4 | 4 | Installation certificate | Chief Electrical Inspectorate | 6 days |
| 5 | 5 | Boiler Registration | Boilers Department | 14 days |
| 6 | 6 | Drug Manufacturing License | Drugs Control Administration | 14 days |
| 7 | 7 | Registration under the Legal Metrology Act, 2009 | Consumer Affairs, Food & Civil Supplies | 15 Days |
| 8 | 8 | Registration under Shops and Establishments Act | LET&F | 1 Day |
| 9 | 9 | Registration of Establishment under the Inter State Migrants Workmen (RE&CS) Act, 1979 | LET&F | 30 Days |
| 10 | 10 | Renewal of Consent for Operation (under Water Act 1974 and Air Act 1981) by TSPCB | EFS&T | Green – 7 Days; Orange – 21 Days; Red – 30 Days |
| 11 | 11 | Renewal of Factory License | LET&F | 3 Days |
| 12 | 12 | Renewal of Boilers License | LET&F | 14 days |
| 13 | 13 | Registration of Steam Pipe line from Boilers Department |
Boilers Department | 14 days |
| 14 | 14 | Final completion / Occupancy certificate | DT&CP / IALA / HMDA / KUDA / UDAs |
8 days
|
Renewal
| Renewal | |||
| S.No. | Renewal of | Department | Time Limit |
| 1 | Consent for Operation (CFO) | TSPCB | 7 Days |
| 2 | Factory Licence | Factories Department | 3 Days |
| 3 | Boilers Licence | Boilers Department | 7 Days |